Dewa to add 600MW of clean energy

Dewa issued a Request for Qualification (RFQ) for developers to build and operate the fifth phase of the solar park with a capacity of 900MW.

Share
[representational image]
AFPGetty Images
[representational image]

HE Saeed Mohammed Al Tayer, MD & CEO of Dubai Electricity and Water Authority (DEWA), Al Tayer was briefed on the progress of the 300MW second phase of the solar park, which will be operational in late June. Construction of the 300MW third stage started earlier this year and will be operational in 2020.

The solar park is the largest single-site solar park in the world, based on the Independent Power Producer (IPP) model. It will generate 5,000MW by 2030 with investments of up to AED50bn.

Related

The first stage has a capacity of 200MW and became operational in May 2018. It uses unique technologies, including over 800,000 self-cleaning solar cells that use robots to maintain efficiency. This stage provides over 60,000 residences with electricity, reducing over 270,000 tonnes of carbon emissions every year. Dewa established Shuaa Energy 2 with a 60% stake in the company in partnership with the Masdar-led consortium, and Électricité de France (EDF), through its subsidiary EDF Énergies Nouvelles. The consortium owns the remaining 40% of the company; Masdar owns 24% and EDF Énergies Nouvelles owns 16%. The international consortium led by the renewable energy contractors GranSolar and Acciona from Spain and Ghella from Italy are handling the engineering, procurement, and construction (EPC).

The 13MW photovoltaic first phase of the Mohammed bin Rashid Al Maktoum Solar Park became operational in 2013. The 200MW photovoltaic second phase of the solar park was launched in March 2017, and the 800MW photovoltaic third phase will be operational by 2020.The fourth phase of the solar park is the largest single-site solar IPP project in the world and combines CSP and photovoltaic technology. The phase will use hybrid technologies to produce 950MW of clean energy.

Dewa issued a Request for Qualification (RFQ) for developers to build and operate the fifth phase of the solar park with a capacity of 900MW. The phase will use photovoltaic solar panels based on the IPP model and will be commissioned in stages from Q2 2021.