SNC-Lavalin wins $70m contract to build three substations in Meydan One

The substations are expected to be operational in late 2019.

Share
SNC-Lavalin will undertake the full design and delivery of all three 132/11kV gas insulated switchgear (GIS) substations in Meydan One.
SNC-Lavalin will undertake the full design and delivery of all three 132/11kV gas insulated switchgear (GIS) substations in Meydan One.

SNC-Lavalin has been awarded a $70m contract to provide engineering and procurement services for the Meydan Group’s Mahra, Jeyad and Forsan 132/11kV substations for the Meydan One development in Dubai.

SNC-Lavalin will undertake the full design and delivery of all three 132/11kV gas insulated switchgear (GIS) substations, including the civil design and delivery of three two-storey buildings, all electrical equipment and electro-mechanical works.

Deliverables for each of the three substations include the design, procurement, installation and commissioning of the 132kV and 11kV switchgears, 132/11kV 35/50MVA transformers, shunt reactors, capacitors, earthing transformers, associated control and protections, and remote end integration.

Related

The substations are expected to be operational in late 2019.

Marie-Claude Dumas, president, Clean Power, SNC-Lavalin, said: “SNC-Lavalin has considerable experience in delivering substations, with over 2,500 completed around the world over the last 100 years, and we’re proud to be using that experience to successfully and safely deliver this project. The Mahra, Jeyad and Forsan substations are a key part of this exciting development, helping to form the backbone of the electrical infrastructure that will address growth demand in the new Meydan One development.”