The build is slated for handover in December 2019 thanks to “accelerated works”.

Share
Nearly a third of work concerning heating, ventilation, and air conditioning (HVAC) has been done.
SUPPLIED IMAGE
Nearly a third of work concerning heating, ventilation, and air conditioning (HVAC) has been done.

For the latest MEP news from the UAE, Gulf, and around the world, follow us on Twitter and LinkedIn.

Azizi Developments has reached the 60% milestone at its Azizi Aura project in Downtown Jebel Ali.

Related

Slated for completion in December 2019 thanks to “accelerated works”, the development consists of 479 units, including 349 studio, 87 one-bedroom, and 43 two-bedroom apartments.

Nearly a third of work concerning heating, ventilation, and air conditioning (HVAC) has been done, as well as almost 16% of the overall finishing.
The second fix of MEP works is currently at 35%, while the façade stands at 28%.

Farhad Azizi, CEO of Azizi Developments, said: “This tower is yet another testament to our commitment to timely delivery and build-quality.